Hitsaus Referenssejä

2021-2023 Porin Teollisuusputki Oy. Metsä Fibre, Kemi. BTT. Support installations and welding, prefabrication, welding, and installation of pipelines under supervision.

2023-2024 Porin Teollisuuputki Oy. Meyer Turku

2024 Porin Teollisuuputki Oy. Stora Enso Oulu 0750-projekti

2024 Metsä Fibre. Kemi Vuosihuoltoseisokki

2024 Porin Teollisuusputki Oy. Vantaan Energia

2024 CTS Nordics Espoo

More Additional referencens add to the list
2024 Andritz.Pietarsaari. Huoltoseisokin luukku-ja tulivahtityöt.

2024 Lassila & Tikanoja. Harjavallan suurteollisuuspuiston vuosihuollon miehitys

2024 Corex Finlad. Pori. Jatkuva huolto sekä huoltoseisokit

2022-2024 ETS-Lingren Oy. Alueena koko Suomi. Asennus ja rakennustyöt

  • 2021 Andritz, Mondi Dynäs, Sweden. Fire and hatch monitoring for the project.
  • ⁠ ⁠2021 Neste, Porvoo refinery. Pressure washing of pipeline sections and suction truck services. Flange installation project for pipeline sections.
  • ⁠2020-2021 Kutepa Oy, Kongsberg Maritime Finland Oy. Welding and installation of stainless steel gas pipelines with 100% imaging.
  • ⁠ ⁠2020-2021 Fortum Waste Solutions Oy, Vaasan Kemira. Removal and cleaning of hazardous materials in pipelines and tanks, demolition work, scaffolding, and removal of hazardous substances under supervision.
  • ⁠ ⁠2020-2021 Nordic Power Service Oy, Stora Enso, Oulu. Welding and installation work.
  • ⁠ ⁠2020-2021 SKM Service Oy / Bravida, Stora Enso, Oulu. Welding and installation work.
  • ⁠ ⁠2019-2020 Clean Steel Oy. Cleaning of thermal boilers across various sites in Finland.
  • ⁠ ⁠2020 Andritz, Stora Enso OCO Project, Oulu. On-site HSE management.
  • ⁠ ⁠2018-2020 Fortum Oy, Inkoo coal-fired power plant scaffolding work.
  • ⁠ ⁠2020 Andritz, Metsä Fibre, Rauma. Batch cooker welding and installation work.
  •  2020 Versowood, Hankasalmi. Sawmill line dismantling.
  • ⁠ ⁠2020 Versowood, Vierumäki. Sawmill line dismantling.
  • ⁠ ⁠2020 Umacon Oy, Stora Enso Oulu OCO Project. Dismantling and relocation of slitting and calendering equipment.
  • ⁠ ⁠2020 Jartek Oy, Versowood, Hankasalmi. Sawmill line installation.
  • ⁠ ⁠2020 Jartek Oy, Versowood, Vierumäki. Sawmill line installation.
  • ⁠ ⁠2018-2019 Are Oy, Break Sokos Hotel, Vantaa. Pipe welding and installation.